A replacement water main from North Burnaby to New Westminister, The Douglas Road replacement is approximately 2 km's long primarily along, McGill, North Rosser Avenue and Albert Street.
Graham Construction
The scope of work was primarily the installation of 2 km's of 1.5 meter diameter steel pipe in a dense residential zone. In addition to this, our crews installed 800 m of 200 mm water main, 750 m of sewer services and 2 km of asphalt and curb/gutter removal.
Value: $4.2 Million