Trio featured a main intake and head pond and a tributary tap, flow will be diverted by the intake through the main penstock to two powerhouses, the construction of a new 28 megawatt run of the river hydroelectric dam. This project is located 80 km north west of Harrison Hot Springs
Kingston Construction
Springline's scope included the installation of the 2.5 km of large diameter penstock (1.2 m - 1.6 m in diameter), mass excavation and earthwork including a 7.5 m high dam, clearing and grubbing, road construction and rock excavation. This work was carried out on mountainous terrain.
Value: $25 Million